Due to the increasing demands upon the existing on-airport car rental
facilities, the need for a consolidated rental car facility has become
necessary. Traffic flow around the airport, and air quality will benefit
from the consolidation. The new Consolidated Rental Car Facility (CONRAC)
will be located south of Camp Creek Parkway and west of Interstate
85. Construction started on March 28, 2006 and is scheduled
to be complete early 2009.
Major projects include:
Facility: The facility will accommodate
the ten rental car companies (with room for expansion in the future)
and will provide for approximately 8,700 ready and return spaces.
Additionally, this project will include accommodations for customer
service centers, storage and minor maintenance areas, wash lane facilities
and vehicle fueling positions to support the quick turn around operation
used by the rental car agencies.
Vehicle Access Route: A new four-lane
airport access road will connect the airport roadway system to the
CONRAC Facility. This roadway provides the vehicular access and egress
to the facility. The roadway will include a vehicular bridge that
will cross Interstate 85, U.S. Hwy 29, CSX Railroad and the MARTA
tracks.
Automated People Mover (APM) System: To accommodate passengers
to and from the Central Passenger Terminal Complex (CPTC) and the
new CONRAC Facility, a new APM will be built. This APM will be similar
to the one already in operation at the Airport, which takes you from
concourse to concourse. The APM track will be elevated over I-85 and
U.S. Hwy 29 and will have three stops including one near the Georgia
International Convention Center.
Over the next three years, the infrastructure for the
elevated guideway system and APM connecting the airport to CONRAC
is being constructed. The project will impact the flow of pedestrian
traffic in the Ground Transportation Center, an area where passengers
connect with hotel, motel and rental car agency shuttles; taxicabs;
limousines; and buses to on and off-site parking lots.
» Learn more about the Automated People Mover (APM)
During construction of the APM system, many ground transportation
services will have their staging locations altered. Customer service
representatives and special color coordinated signs will be available
to assist passengers at the airport.
BAGGAGE SECURITY CONSTRUCTION PROJECT
Hartsfield-Jackson Atlanta International Airport transitioned into the
last phase of its in-line baggage security screening construction project
at both terminals. Roadway construction is completed and System Testing
and Commissioning continue until April, 2006 for Terminal South and
June, 2006 for Terminal North.
Please note the following
changes at Terminal South:

Kiss N Fly at Terminal South remains open and
is a drop-off area.
Baggage check-in is still available at the Kiss N Fly area.
Passengers may be picked up at the curb
and dropped off at the Kiss N Fly area for baggage check-in.
Changes at Terminal North:
Passengers may be dropped
off and picked up at both inner and outer curbs.
Photo Gallery
Phase I Phase II
FACT SHEET

The construction project is called the TSA Hold Baggage Screening Project.
Its scope calls for the construction of two underground facilities,
one at the North and South terminal, to electronically screen checked
baggage in an automated manner.

Other goals of the project are to reduce congestion in our facilities
by removing the large screening machines from the ticketing lobbies, and
to minimize the impact of the project on all users of H-JAIA.

The facility at the North Terminal is roughly 67,000 square feet. The
South Terminal facility is approximately 54,000 square feet. Each will
be constructed under the curbside in front of the terminal. There will
be two phases of construction with the portion at each Parking Deck, under
the Outer Roadway, being constructed first and the portion against the
Terminal, under the Inner roadway, being constructed last.

The Phase One construction, for both the north and south facilities, will
take approximately six months. For the Phase Two portion, the south will
require six months and the north will require an additional six to nine
months.

The process to construct each facility will involve closing each portion
of the road, digging out the dirt under the road, constructing the facility,
reinstalling the roadways over the facility and reopening that portion
of roadway. Almost all of the public impacts will cease after the Phase
Two portion is constructed and the roads reopen.

After the facilities are constructed, the equipment to electronically
screen each piece of checked baggage will be installed. New conveying
systems to transport the bags from the airline check-in positions to the
screening area will also be installed. In total, about 20,000 linear feet
of new conveyors will be installed in the new facilities. That is almost
four miles of new conveying systems.
Please check this site regularly for construction information on changes
that could impact your visit to the airport. The following projects are
presently underway at Hartsfield-Jackson:
Other
Activities:
There are several unique construction activities on-going in and around
Hartsfield-Jackson Atlanta International Airport. These activities include
but are not limited project undertaken by; The Transportation Security
Administration, the Airlines, concessions and support businesses at the
airport.
Last Updated: March 30, 2006.